Fargo's New Elementary School Takes Shape
FARGO — Most of the focus since the summer demolition of Fargo Public Schools’ oldest school building has been on underground work. But now, a new elementary school is beginning to materialize on the site at 1025 Third St. N.
Construction crews began placing precast concrete walls for the new Horace Mann Elementary School on Monday, Nov. 16.
Walker Busse, project manager from general contractor Kraus-Anderson, said they’ve been looking forward to this date for a while. “We call it ‘going vertical’ on the building, and it’s starting to take shape,” Busse said, standing on the sidewalk outside the fenced-off construction site.
The new $45 million Horace Mann Elementary will serve students in grades K–5 from Horace Mann, Roosevelt and Madison elementary attendance boundaries. Until then, students affected by the construction or new boundaries are attending grades K-2 at Madison and grades 3-5 at Roosevelt.
The project is being financed by a bond issuance through the district’s building fund.
Built in 1915, Horace Mann was targeted for demolition due to its advanced age, challenges in making safety upgrades, lack of space for serving lunch, and absence of collaborative spaces, the district said previously. Demolition began in late June and crews hauled away debris for weeks after that.
Since then, the contractor has been working on tasks that people passing by didn’t see, including soil improvements and laying the building’s footings and foundation, leading up to placement of the precast walls.
The concrete walls are being poured in-house at Taracon Precast in rural Hawley, Minnesota, and hauled to the school site on semis. Wysan Precast Services, with offices in Moorhead and Hawley, is using a large crane to place the large panels.
Busse said workers plan to erect 8 to 12 panels each day, for a total of up to 140 panels in all. The smaller panels, like those erected Monday, weigh between 10,000 and 15,000 pounds, he said. The heaviest ones to be placed later for areas of the school that are three stories high weigh between 45,000 and 52,000 pounds each. “These first ones will go fairly quickly, but the larger panels will take a little bit more time for each piece,” Busse said.
The precast walls should all be in position by around Christmas time, Busse said. Then will come structural steel work, a start on the building’s roof, and a shift to construction on the building’s interior.
When the building is finished by the end of 2027 or early 2028, it will be turned over to Fargo Public Schools, which will begin furnishing and supplying the new school to welcome students in fall 2028.