Construction Project Updates – Week of 10/26/26 - City of Keene (.gov)

Construction Project Updates - Week of 10/26/26 - City of Keene

City of Keene

Services

  • Applications & Forms
  • Building Permits
  • Cemeteries
  • Elections & Voting
  • Events Schedule
  • Human Services & Welfare
  • ... (rest of the list not shown in the provided text)

Departments

  • Online Services
  • Phone Numbers & Hours
  • Airport
  • Assessing
  • City Clerk
  • Community Development
  • ... (rest of the list not shown in the provided text)

Construction Updates (October 23, 2026)

The City of Keene Public Works Department shares the following construction and maintenance activities for the week of October 26, 2026:

Central Square:

On Monday, October 26, Casella Construction, Inc. will continue installing water and sewer utilities. Parking spots and areas within the active construction zone may shift or close, with detours in place. Traffic and parking will return to normal by the end of the workday. For details, refer to the Downtown Construction press release.

Bartholomew Court:

Starting Monday, October 26, at 7:00 a.m., Bazin Brothers Trucking will complete final paving. The road will be closed during construction. Visitors to Public Works should park at Keene Ice. Work is expected to take one day, with normal traffic restored by the end of the day.

Marlboro Street:

On Monday, October 26, Bazin Brothers Trucking will work on landscaping, signage, and cleanup between Eastern Avenue and Main Street. Traffic patterns may be adjusted around active work areas.

George Street Bridge:

On Monday, October 26, New England Infrastructure, Inc. will continue site cleanup and utility installations. George Street will remain closed with traffic detoured. Work is expected to continue for about five more weeks before pausing for winter.

Robin Hood Park Pool:

Beginning Monday, October 26, Weston & Sampson CMR will start demolishing the concrete pool deck as part of the Robin Hood Park Pool project.

Morin Avenue:

Starting Tuesday, October 27, Frank Lucius Construction will install water and sewer services near 28 Morin Avenue. Morin Avenue will be closed to through traffic. The work is expected to take one day, with normal traffic restored.

Kelleher Street:

Beginning Wednesday, October 28, Mike Pappas Construction will install a water service near the intersection with Marlboro Street. Traffic will be shifted to maintain two-way travel. The work is expected to take one day, with normal traffic restored.

For any questions, please contact ... (the rest of the contact information is not shown in the provided text)