Construction Update: Weeks of 10/12/26 and 10/19/26 - Columbia Neighbors

Construction Update: Weeks of 10/12/26 and 10/19/26

Construction

October 09, 2026

An aerial view of the site at 125th Street and 12th Avenue. View a PDF version of this week's update.

  • Demolition: The demolition of the existing slab on grade on the west part of the site is underway, which may cause some noise and vibrations.
  • Grading: The site is being imported with clean fill and graded to meet new elevations.
  • Underground Structures: Backfilling of underground stormwater concrete structures and piping is in progress.
  • Electrical Work: The project has started electrical work for the new light poles.
  • Debris Disposal: Trucking of soil and concrete debris off-site to disposal facilities is taking place.
  • Integrated Pest Control: Integrated pest control measures are being implemented sitewide.

What to Expect:

Work hours are from 7:00 a.m. to 3:30 p.m., Monday to Friday. Expect typical construction-related impacts, including noise, vibrations, material deliveries, and other disruptions.