Construction Update: Weeks of 11/2/26 and 11/9/26

October 30, 2026

An aerial view of the site at 125th Street and 12th Avenue. View a PDF version of this week's update

Site at 125th Street and 12th Avenue:

  • Importing clean fill and topsoil to grade the site to meet new elevations

  • Backfilling underground stormwater concrete structures and piping

  • Soil compaction and testing

  • Running conduits and piping for the new light poles

  • Installing piping for the irrigation system

  • Integrated pest control sitewide

  • Please note that all activities are subject to change based on weather and other field conditions.

What to Expect:

Work hours are 7:00 a.m. to 3:30 p.m., Monday to Friday.

Expect noise, vibrations, delivery of materials, and other impacts typically associated with construction projects.