Site located at 125th Street and 12th Avenue:

  • Importing clean fill and topsoil to grade the site to meet new elevations.
  • Installing new sidewalk at 125th Street and a 20-foot concrete walkway.
  • Planting trees and shrubs in the east planting area.
  • Commencing the installation of the new site perimeter fence.
  • Soil compaction and testing are ongoing.
  • Running conduits and piping for the new light poles.
  • Installing piping for the irrigation system.
  • Implementing integrated pest control sitewide.