Great Streets Downtown Hyannis: Weekly Construction Update (November 2 – 6, 2026)
Oct 30, 2026
Great Street - Hyannis
Roadwork Notices
As construction continues on the Great Streets Downtown Hyannis project, the Town of Barnstable Department of Public Works (DPW) will share weekly updates to keep downtown businesses, residents, and stakeholders informed about upcoming activities and potential impacts.
Weekly Construction Update: November 2-6, 2026
Work Hours:
Monday–Friday, 7:00 AM–3:00 PM
Traffic Impacts:
Intermittent lane closures will continue with no anticipated road closures.
Where Crews Are Working & What’s Happening:
- Six-Points Intersection: Drainage, excavation, and conduit installation will continue in preparation for a new roundabout.
- Main Street (Various Locations): Crews will build accessible curb ramps to enhance pedestrian accessibility.
- North Street: Marking out locations will begin in preparation for upcoming curbing work.
Looking Ahead:
As construction progresses, stakeholders can expect:
- Curb Ramp Construction: Work will progress in stages, including pavement removal, area preparation, and pouring new concrete.
- Progress Along Main Street: Crews will work progressively on one side of the street before moving to the other.
- Direct Business Notifications: The DPW will notify affected businesses directly with more specific information about work locations and schedules.
Stay Informed:
We understand the challenges construction in a busy downtown area can present. We appreciate your patience and cooperation during this period.