/India gives update on nuclear construction projects : New Nuclear
npressfetimg-404.png

India gives update on nuclear construction projects : New Nuclear

16 December 2022

Minister of State Jitendra Singh confirmed The federal authorities’s plans for 21 new reactors – collectively with these already beneath enchancment – and gave an replace on the progress of The numerous tasks in a written reply to the Lok Sabha.

Coring of basis piles for Gorakhpur-1 (Picture: NPCIL)

Based mostly on Singh’s assertion, The subsequent tasks are classed by The federal authorities as “beneath enchancment”:

  • Kakrapar 3 & 4: Kakrapar 3 was related to the grid in 2021 and the enterprise To assemble two 700 MWe pressurised heavy water reactors (PHWR) is classed as 97.12% full (as of October 2022). Anticipated completion 2023.
  • Rawatbhata 7 & 8: 700 MWe PHWRs, 88.88% full, expected completion 2026
  • Kudankulam 3 & 4: Russian-currentd 1000 MWe VVER pressurised water reactors, 63.67% full, expected completion 2025.
  • Kudankulam 5 & 6: 1000 MWe VVERs, 12.89% full, expected completion 2027.
  • Kalpakkam: 500 MWe prototype quick breeder reactor, 97.64% full, expected completion 2024.

The authorities additionally packages Gorakhpur 1 & 2 – each 700 MWe PHWRs – as “beneath enchancment” with an expected completion date of 2029. Foundation piles for the nuclear islands have been fulld and work is beneath method on fullly different constructings and constructings On the Haryana website, in accordance to Singh’s assertion.

The following tasks – all 700 MWe PHWRs – have been accorded administrative approval and monetary sanction:

  • Kaiga 5 & 6
  • Gorakhpur 3 & 4
  • Chutka 1 & 2
  • Mahi Banswara 1 & 2
  • Mahi Banswara 3 & 4

Pre-enterprise website actions and bulk procurement of prolonged-lead gear are beneath method for these tasks, all of That are expected to be fulld “progressively by 2031”. Excavation for Kaiga 5 & 6 has already begun.

“Nuclear power can current the nation with clear base-load power and scale again dependence on coal and conventional sources of power Inside the Long time period. Nuclear Power would additionally complement clear renewable power,” Singh said.

Earlier this yr officers from India’s Division of Atomic Energy said the nation was getting ready To start constructing 700 MWe PHWRs in fleet mode from 2023, starting with Kaiga 5 & 6.

Researched and written by World Nuclear Information