Jones Library Construction Update: Meeting Report - November 16, 2026

This meeting, held via Zoom and recorded, featured the following attendees:

  • Austin Sarat (Jones Library trustee and chair)
  • Sharon Sharry (library director)
  • Paul Bockelman (town manager)
  • Sean Mangano (town finance director)
  • George Hicks-Richards (library building facilities supervisor)
  • Alex LeFebvre
  • Christine Gray-Mullen
  • George Ryan (town councilor)
  • Bob Peirent (town special projects manager)

The primary focus of the Jones Library Building Committee (JLBC) meeting was to provide updates on construction progress.

Construction Update

  • Exterior Work: Completion of sidewalk, paving, and curb installation, Goshen stone seat wall construction using salvaged materials from the previous garden, and wooden railing replacement on the eastern side.
  • Interior Work: Progress on the main staircase, drywall, painting, elevator installation, acoustic ceiling tiles, electrical, plumbing, and HVAC systems, with millwork installation ongoing.

Schedule Update

Trey Logie from Colliers (Owner’s Project Manager) reported no changes to the schedule, with the following estimated timelines:

  • Substantial completion: End of March
  • Furnishings and equipment installation: Mid-April
  • Closeout: End of May
  • Public opening: End of June or early July

Lighting and Construction Hours

Neighbors raised concerns about lights being on after construction hours. Logie acknowledged the violation of the scheduled work hours (7:30 a.m. - 4:30 p.m.) and confirmed that timers have been adjusted to 6 a.m. - 5 p.m.

Interior Design

The meeting packet materials include details on the proposed interior color palette, which is available for review.

Invoices and Contingency

A total of $2,233,821.25 in invoices was approved by the committee:

  • Colliers (Owner’s Project Manager): $39,620.73
  • Fontaine Bros. (General Contractor): $2,115,536.10
  • FAA (Designer): $52,261.00
  • NV5 (Commissioning Agent): $5,325.00
  • Slobody (rent at temporary location): $21,078.42