Olio Road detours, 116th Street restrictions highlight Fishers road report
October 31, 2026
LarryInFishers.com
Major detours at Southeastern Parkway and Olio Road continue to affect Fishers drivers, while holiday light installation will bring additional lane restrictions on 116th Street Nov. 2-3, according to the city’s weekly road construction report.
Phase two of the Southeastern Parkway and Olio Road roundabout reconstruction remains underway, with work anticipated to continue through the end of the year. Drivers cannot travel directly north or south on Olio Road through the roundabout.
- Southbound traffic approaching from the north is directed west onto Campus Parkway/146th Street.
- Northbound drivers approaching from the south must detour using 136th Street and the new connection to Southeastern Parkway.
- The roundabout’s fifth leg has permanently closed.
Nearby businesses, hospitals and medical offices remain accessible. Drivers should review the detour maps in the report below before traveling through the area.
At 116th Street and Allisonville Road, milling and paving are complete, but intermittent lane restrictions continue for striping, traffic signal work, and restoration. Sidewalks within the project area remain closed, and businesses remain accessible.
On Monday and Tuesday, Nov. 2-3, Department of Public Works crews will install holiday lights on street trees along 116th Street between Fishers Center Drive and Lantern Road. The work will require intermittent closures of the right lanes in both directions.
Other work includes:
- A detour on 136th Street between Southeastern Parkway and Prairie Baptist Road
- Continuing restrictions on USA Parkway north of 106th Street
- Possible periodic lane restrictions for utility relocation at 131st Street and Brooks School Road
Resurfacing crews also will continue working in Springs of Cambridge during the week of Nov. 2.
Construction schedules are weather-dependent and subject to change.
The complete report, including detour maps and additional project updates, is available below:
Road Closures and Traffic Impacts – At a Glance
- USA Parkway Widening: Lane restrictions in place
- 136th Street Widening: Detour in place between Southeastern Parkway & Prairie Baptist Road
- 116th Street & Allisonville Road: Intermittent lane restrictions for ongoing operations
- Southeastern Parkway & Olio Road Roundabout: Phase two in place with major closures impacting traffic
- 131st and Brooks School Road: Utility relocation in progress – periodic lane restrictions are possible
Road Resurfacing
Continuing into phase two of resurfacing in Springs of Cambridge
Holiday Light Installation
On Monday and Tuesday of the week of November 2 the Department of Public Works crews will be installing holiday lights on street trees from Fishers Center Drive to Lantern Road. Work will require the right lanes (Eastbound and Westbound) to be taken intermittently as needed.
Major Closures and Detours
- 136th Street Widening – Southeastern Parkway and Prairie Baptist Road:
- Phase 2
- This next phase will focus on improvements between Southeastern Parkway and Prairie Baptist Road.
- 136th Street is closed to through traffic within the project limits. Drivers should follow the signed detour route using Southeastern Parkway and Prairie Baptist Road to reconnect with 136th Street.