Silicon Valley BART extension hits construction milestone - San José Spotlight

Transportation Milestone Celebrated in Silicon Valley BART Extension

Workers have achieved a significant construction milestone in the $12.7 billion Silicon Valley BART extension project, completing the excavation and reinforcement of an 83-foot-deep hole on a former rail yard property near PayPal Park. This shaft will serve as the launch point for the massive boring machine that will drill a 5-mile tunnel for the new BART tracks.

The project, over a decade in the making, has faced delays, cost overruns, and controversies, including opposition to its single tunnel design. However, the recent progress on one of the first major structures is expected to boost confidence in the project's progress.

"What’s so exciting now is you can stand at the top of that ramp, or at the bottom of that shaft, and really imagine what it’s going to be like," said Tom Maguire, VTA's chief megaprojects officer. "You can feel where the trains will go and envision a subway running here someday."

Completed in September and October, the excavation and concrete pouring for the underground structure marked a significant step forward. The shaft is connected to an 1,100-foot ramp that will accommodate trains entering or exiting the planned Santa Clara BART station.

The launch shaft will facilitate the boring machine's positioning at the correct depth, beginning tunneling work in early 2028 at a rate of 30-40 feet per day.

"Digging a hole may sound simple, but considering the soil conditions, the concrete reinforcements, and the structure's complexity, it’s been a considerable undertaking," Maguire noted.

Crews have logged 3.7 million person-hours at the site without any serious injuries, according to VTA officials. The 5-mile tunnel's excavation is projected to take 40 months, followed by track laying, station building, and infrastructure installation.

Initial projections for the project in 2014 estimated a cost of $4.7 billion and a 2026 service start. However, material cost spikes due to the COVID-19 pandemic and other factors have doubled the projected cost and pushed the opening date to 2037.

Despite setbacks, San Jose District 3 Councilmember Anthony Tordillos praised the project's progress, stating, "This is an exciting milestone... setting the stage for the start of tunnel boring and paving the way toward a more connected San Jose."