Nuclear Regulatory Commission Approves Construction of Advanced Reactors in Texas
The Nuclear Regulatory Commission (NRC) this week issued a permit for construction of four next-generation nuclear reactors at a petrochemical complex on the rural Gulf Coast of Texas.
The Long Mott Generating Station
The Long Mott Generating Station, developed by chemical giant Dow and nuclear startup X-energy, is one of two flagship projects selected by the U.S. Energy Department in 2020 for its Advanced Reactor Demonstration Program.
“This milestone marks a significant step forward,” said Mike Goff, principal deputy assistant secretary for nuclear energy, in a press release. “The NRC’s approval demonstrates meaningful progress toward deploying advanced reactors.”
Revolutionizing the Nuclear Sector
The Texas project is at the leading edge of a new generation of reactor designs that could revolutionize the commercial model for atomic energy. These designs replace the gargantuan construction projects currently required for nuclear power plants with small, modular units that can be produced in factories and then shipped and assembled onsite at industrial installations, from data centers to petrochemical plants.
“We understand that owning a nuclear facility is a different kind of responsibility. We do not take that lightly.” — Kreshka Young, North American business director for energy and climate at Dow
Safety and Concerns
Dow plans to install four 80-megawatt reactors by X-energy at its Seadrift Operations complex. Unlike traditional reactors, these units won’t require towering containment structures or a 10-mile emergency planning zone, thanks to revolutionary safety features.
X-energy CEO J. Clay Sell has claimed that the company’s Xe-100 unit is "physically impossible to melt down." However, Diane Wilson, a retired fourth-generation shrimper and director of San Antonio Bay Waterkeeper, remains skeptical.
"Frankly, it’s outrageous. This is outrageous." — Diane Wilson
She points out that spent fuel will be stored indefinitely on-site as nuclear waste, as the U.S. still lacks a permanent national disposal site.
Legal Challenges and NRC Approval
In 2025, Wilson’s organization filed legal challenges to the project’s permit application over safety concerns, which were ultimately dismissed by the NRC. The agency approved Dow’s reactor construction permit after an expedited review under executive orders from President Donald Trump aimed at accelerating the national energy sector.
"We delivered on the 18-month schedule, proving we can do rigorous safety reviews on predictable timelines that move advanced nuclear technology from design to construction." — Ho K. Nieh, NRC Chairman
Future Prospects
Dow still needs to make a final decision to proceed with the project, which could begin before 2030. If successful, it would provide a blueprint for other industries to install dedicated, onsite power generation.
"The nuclear industry is watching this project very closely." — Martin O’Neal, general counsel for the Nuclear Energy Institute
This story is funded by readers like you. Our nonprofit newsroom provides award-winning climate coverage free of charge and advertising. We rely on donations from readers like you to keep going. Please donate now to support our work.