Several Major Lloyd Expressway Projects Nearing Completion
EVANSVILLE – Think of it as an early Christmas present. Several of the biggest construction projects on Evansville's Lloyd Expressway are expected to wrap by the end of the year, the company behind the overhaul told the Courier & Press.
Nicole Minton, a representative with Lochmueller Group and public outreach manager for the expansive and yearslong "Lloyd4U" project, said intersections at Burkhardt Road and Cross Pointe Boulevard, as well as multiple interchanges on the West Side, should be "fully functional" before the holiday.
“I was hoping to have most if it wrapped by the holiday shopping season’s start – so next week would have been ideal," she said Wednesday, Nov. 18. "We still have a little work to get done before then, but (we're) definitely wrapping up in December.”
Red Rank Road, a swamped intersection leading to the West Side Walmart and the busy shopping area along Pearl Drive, has been under construction since 2024. Minton predicts dual displaced turns in each direction, similar to the design at Lloyd's reconfigured crossing with Stockwell Road, could open as early as Black Friday.
Other work will extend into 2028. Here's a breakdown of the project's status and upcoming openings:
West Side:
- Left turns off the Lloyd Expressway onto Red Bank Road will soon be unrestricted.
- Work between Wabash Avenue and Rosenberger is slated for 2028.
- At St. Joseph Avenue, crews will extend left-turn lanes and add a right-only lane.
- The Barker off-ramps will be reconfigured, with the southbound Barker ramp removed and a stop sign installed.
East Side:
- Displaced left turns at Burkhardt Road, especially between the eastbound Lloyd Expressway and North Burkhardt, are expected to finish by mid-December.
- Cross Pointe Boulevard's dual displaced left turns will also be completed soon.
Minton noted that while most work will be finished by December, some cleanup and finishing touches, like painting curbs and replacing temporary lines, may extend into 2027.