Wayne County orders halt on Google data center construction - The Detroit News

Wayne County Halts Google Data Center Construction over Drainage Concerns

Wayne County has ordered a halt to the construction of a hyperscale data center campus in Van Buren Township, citing negative impacts on county drainage infrastructure.

On November 20, the county issued a stop work order to Panattoni Development Company due to unauthorized construction within the county's road right-of-way and violations of the Wayne County Stormwater Control ordinance. The order remained in effect as of November 23, according to county spokesman Matt Allen.

The stop work order follows the initiation of construction on the data center, which will be used by Google upon completion. Spanning 282 acres east of Haggerty Road and north of I-94 North Service Drive, the campus will feature five buildings, including three data processing facilities ranging from 87,000 to 300,000 square feet. It is projected to consume between 2 to 3.6 million gallons of water daily and draw 1 gigawatt of power, according to planning documents.

The Detroit News obtained aerial images of the construction site on November 20, just over a month after Van Buren Township's planning commission approved the site plan.

Allen acknowledged the site plan approval but emphasized that Panattoni failed to secure a permit for the construction site's location adjacent to a county drain.

"When you abut a county drain, you must have a runoff plan and other measures in place due to heavy rainfall," Allen explained. "There's a risk of silt and mud entering the sewer system."

In a statement to The Detroit News, a Panattoni spokesperson expressed the company's commitment to compliance:

"Coordination with local agencies is a standard part of the development process, and our team is actively collaborating with County officials to address the items in question, provide clarifications where needed, and move forward with the project."

The stop work order highlighted the significant impact of construction activity on multiple county drains within the site, posing "substantial flooding risks." It deemed the construction "unauthorized" until Panattoni obtains a construction permit from the county and reaches agreements with each drainage district or the Wayne County drain commissioner.

Allen noted that the county initially attempted to access the construction site on Thursday, November 19, but was denied entry due to the late hour. They successfully served the order on Friday, November 20. Workers were present on the site on Monday, November 23, securing tools.

Allen expressed optimism about the resumption of construction, stating, "That's what architects, engineers, and project managers do."