Why are so many Yorkshire development projects end up delayed? - BBC

Why Construction Projects Experience Delays?

It's an increasingly common scenario - a local authority announcing that a major development won't be delivered on time. Across Yorkshire, key construction projects have been beset by delays, in some cases struggling to progress and ending up years behind schedule. Councils and other public bodies often have to explain to taxpayers why these schemes are delayed or over budget, and the reasons can be wide-ranging.

One example is Stocksbridge, near Sheffield. In 2019, as part of the general election campaign, the government announced major investment in the town. Levelling Up funding of £24m was promised for a new library and business hub. Over the following years, the project was downgraded, and work didn't even start on the site until 2025. It is now not expected to be completed until spring 2027.

Ben Small is a director of Edge, a Leeds-based company which provides consultancy, programme management, building surveying, and technical advice for the construction industry. Edge works on a range of projects, some expected to cost as much as £100m to deliver.

One of the most common reasons given for council-funded developments rising in expense over time is inflation. "The underlying issue around inflation is what's going on in the wider market which can impact on the construction industry," explains Small.

"Often inflation is referred to in terms of what is going on at an international scale, such as in the Middle East, Ukraine, and other parts of the world where often materials and supplies are received to feed our industry here in the UK. There are elements that impact on inflation on an international scale but there's also a great deal going on much closer to home. We often see real challenges within the supply chain, and that could be to do with equipment, services, and trades. So when councils quote that their project is challenged by inflation, it's often a number of factors that are ultimately outside of their control."

In York, the Station Gateway scheme reached a cost estimate of £60m in July, £34m more than the original budget. The project, which began in 2023, was initially expected to be finished by May 2025. An audit earlier this year found "critical" weaknesses in the handling of the project. It said City of York Council had entered a building works contract "at risk", which pushed up costs and caused delays.

Small highlights the lengthy process from the original design stage through to the final construction works. "In the early stages of a design, the brief may not be as well-developed as an architectural designer might like. There can also be a bit of lost in translation between when the architect has finished a design and when it's passed to a contractor."

He emphasizes the importance of clear communication: "It's really important that before an architect's design is taken to market, the client is comfortable with what they are contracting on and everybody is clear as to what is being delivered and for what cost."

In Leeds, a milestone in the city's railway station entrance revamp was reached earlier this month when new steps, lifts, and a taxi rank were opened, but the project began in 2022. The work to the New Station Street gateway was supposed to be finished in autumn 2025, then pushed back to this summer and again to September.

Small suggests that local authorities need to set realistic timescales, even if they are frequently broken. "We work with a number of local authorities and the government sector and what often drives a project is the need for it to be delivered within a certain time frame for a certain cost. Often a business case is developed based on a set time frame and that drives the investment decisions of a council. That timescale is often quite challenging but if that timescale was allowed to slip it ultimately results in an increase in cost."